MENU
Home > Case Studies > Another Quality Minor Works Project by the WMS Team – Chudleigh!

Another Quality Minor Works Project by the WMS Team – Chudleigh!

Location: Lamb Park, Drewsteignton, Devon

Scope of Works:
Removal of existing chimney render and application of new render.
Safe removal of asbestos roof tiles by a licensed subcontractor.
Installation of a brand-new roof structure, complete with insulation.
Replacement of all rainwater goods with modern UPVC components.

Materials Used:
Sand, cement, lime for rendering.
Timber battens and roofing membrane.
Roof insulation.
Man made slate tiles.
UPVC rainwater goods.

Workforce:
Chimney rendering completed by our skilled in-house plastering operative.
Asbestos removal, roofing, and scaffolding handled by trusted specialist subcontractor partners.

Duration:
4 weeks - All delivered with minimal disruption and maximum efficiency. Great work once again by Peter and the Minor Works Team!

Back to Case Studies